Jokeri Light Rail contact lines installed in March

Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.

Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.

The contact line work is scheduled to last until Week 13.

Additional information
Jokeri Light Rail

Text: Jokeri Light Rail

Share
URL copied!

Read more news

Campus Published:

Maari building's new address Sähkömiehentie 5 will change as of January 30, 2023

Sähkömiehentie 3 (Maari building) address will change, the new addressis Sähkömiehentie 5 and will be in use as of January 30, 2023.
Campus, University Published:

Napping pods and energy saving - welcome to participate!

Wellbeing on a Sustainable Campus event brings together campus main themes in sustainability, energy saving, and also all campus users wellbeing.
Campus Published:

Big savings in campus' energy consumption

Aalto community took up energy conservation measures covering the entire Otaniemi campus on 10 October 2022.
Campus, Studies Published:

Napping pods were voted the winner

The 2022 participatory budgeting vote's winner released at the end of November. Resting and daytime naps became the winning theme this year.


The winner of the 2022 participatory budgeting vote was determined at the end of November. Resting and daytime naps became the winning theme this year.