Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule

The construction of Jokeri Light Rail has proceeded ahead of schedule. The rapid pace of construction now means that the light rail line can start operating about five months earlier than planned, i.e. early 2024. The construction in the Espoo section will mostly be finished in 2021.
Image: Jokeri Light Rail

Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished. 

The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.

In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.

Text by Jokeri Light Rail

More information
Jokeri Light Rail webpages

HSY's contstruction site remains in place on Konemiehentie

Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.

Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.

Share
URL copied!

Read more news

Campus Published:

The participatory budgeting project culminated in a happy planting workshop

One Euro for Every Student project culminated in a planting workshop in mid-May on the new garden benches
Campus, Incidents Published:

Changes in traffic arrangements at the intersection of Konemiehentie and Maarintie

Changes in traffic arrangements will start on Monday, May 16 at Konemiehentie in front of the Computer Science building.
Campus Published:

Rakentajanaukio parking are will be widely closed

Rakentajanaukio parking area will be widely closed 16.-18.5. due the process of paving.
Campus Published:

How do you move on campus now and in the future? Let us know and have an impact!

Aalto University is improving sustainable mobility on Otaniemi campus. The survey is an effective way to influence mobility and the flow of traffic on campus. You can also register for a sustainable mobility workshop and participate in a summer-themed draw at the end of the survey.