Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule

The construction of Jokeri Light Rail has proceeded ahead of schedule. The rapid pace of construction now means that the light rail line can start operating about five months earlier than planned, i.e. early 2024. The construction in the Espoo section will mostly be finished in 2021.
Image: Jokeri Light Rail

Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished. 

The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.

In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.

Text by Jokeri Light Rail

More information
Jokeri Light Rail webpages

HSY's contstruction site remains in place on Konemiehentie

Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.

Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.

Share
URL copied!

Read more news

Kampuskysely
Campus Published:

Respond to the campus survey, make an impact, and win wellbeing prizes!

The annual campus survey is once again measuring the functionality and comfort of the campus, that is, the campus experience. The survey is open from October 9 to 31, 2024.
Poikkeustilanne-kuvitus
Campus, Incidents, University Published:

Summer and autumn brings changes at Aalto University metro station

Renovations to Aalto University metro station will close the entrances in summer 2024
1KOMMA5°
Campus Published:

The 1KOMMA5° showroom of smart energy solutions is now located in shopping centre A Blanc

Welcome to the Open House 1KOMMA5° Suomi Showroom from Wednesday to Friday 9.–11.10.2024. 1KOMMA5° provides smart energy solutions to enable carbon-neutral energy in Finnish homes by offering solar panel systems, batteries and electric vehicle charging stations.
Sekajätekasa Ämmässuon jätteenkäsittelylaitoksella.
Campus, Cooperation, University Published:

Recycling campaign starts on Otaniemi campus

We will launch a waste recycling campaign on the Otaniemi campus in early October. The aim is to increase the recycling rate and reduce the amount of mixed waste.