Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule

The construction of Jokeri Light Rail has proceeded ahead of schedule. The rapid pace of construction now means that the light rail line can start operating about five months earlier than planned, i.e. early 2024. The construction in the Espoo section will mostly be finished in 2021.
Image: Jokeri Light Rail

Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished. 

The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.

In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.

Text by Jokeri Light Rail

More information
Jokeri Light Rail webpages

HSY's contstruction site remains in place on Konemiehentie

Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.

Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.

Share
URL copied!

Read more news

Otakaari 1 kyltti Y-siipi
Campus, Studies Published:

Activities from Maarintalo to move to the Undergraduate Centre

Maarintalo will be closed at the end of May.
Otaparkki julkisivu
Campus, University Published:

Otaparkki offers smooth parking for campus visitors

The Otaparkki multi-storey car park and other paid parking spaces on the campus provide parking for guests arriving on campus.
Bar Otapas
Campus Published:

New cosy bar Otapas opens in shopping centre A Blanc

Bar Otapas opens on Friday 1st of March in shopping centre A Blanc. Cozy new meeting place is open from afternoon until late at night.
Poikkeustilanne-kuvitus
Campus, Incidents, University Published:

Water cut in Dipoli 22 Feb at 8-15

There is a planned water cut at Dipoli (Otakaari 24) on Thursday 22nd February starting at 8.00, and it is estimated to end at 15.00.