Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule

The construction of Jokeri Light Rail has proceeded ahead of schedule. The rapid pace of construction now means that the light rail line can start operating about five months earlier than planned, i.e. early 2024. The construction in the Espoo section will mostly be finished in 2021.
Image: Jokeri Light Rail

Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished. 

The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.

In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.

Text by Jokeri Light Rail

More information
Jokeri Light Rail webpages

HSY's contstruction site remains in place on Konemiehentie

Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.

Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.

Share
URL copied!

Read more news

Aalto Space student
Campus, University Published:

Accessible routes in Aalto Space application

You can also choose an accessible route for navigation on campus.
Kolme haalariasuista opiskelijaa metroasemalla
Campus, Studies Published:

Use your voice: 14 000 euros for student wellbeing

In autumn 2025, students were asked to come up with ideas on how the university should spend 14 000 euros to improve student wellbeing on campus. Now it's time to vote for the best idea to be implemented during spring 2026.
Campus Sustainability Champion 2025
Awards and Recognition, Campus, University Published:

Campus sustainability champion: concrete actions for creating hope

The Planetary Practices Workshops series was selected as the Campus sustainability champion 2025.
Sähköauton laturit Kemistintie 1
Campus, Cooperation Published:

More electric car chargers added on campus

Ten new charging devices have been installed on the Otaniemi campus.